2006 Winter Task List for Sulehay Nature Reserve
Task list key: Tasks shown in grey text are complete.
Ref Task reference number (background highlighting: blue - winter only task; yellow - winter or summer task)
Priority 1=highest (safety related), 5=lowest, 0=task not required, S=Summer program, G=Group task.
Grp SVG=Sulehay Volunteer Group, PCV=Peterborough Conservation Volunteers, CON=Contractor, WLT=awaiting Trust decision or action
Tools CS=Chainsaw+PPE, BC=Brush cutter+PPE, HT=Hand tools, H=herbicide+PPE, WS=Warning signs, M=Mower, HC=Hedge cutter, TB=Tractor+Baler, TM=Tractor+Mower, TT=Tractor & trailer,
Days Estimated number of days required to complete task.
Ref Pri-ority Grp Location Tasks Tools Days Date Complete or Planned
               
1 1 SVG EF Cut roadside hedge low. HT, HC 1  
2 3 SVG EF Clear pile of dead regwort to compost hollow in RH (or burn in situ). TT 0.25  
3 3 SVG EF Stock fence in SW and NE corner. Top wire requires re-fixing. HT 0.25  
4 2 SVG RH Kissing gate. Clear nettle and bramble at kissing gate behind tool store. Clear to Compost Hollow. HT 0.5 4-Sep-06
5 2 SVG RH Kissing gate. Clear nettle and bramble at kissing gate between Lower Quarry and Byway. Clear to Compost Hollow. HT 0.25  
6 2 SVG RH Kissing gate. Clear nettle at kissing gate leading from Byway towards Calcining Banks. Clear to Compost Hollow. HT 0.25  
7 3 SVG RH Calcining Banks. Established ongoing plan to mow the coarse grasses area in 25% sections on four year cycle. Cut this year's area adjacent to last year's cut area. Clear arisings to local burn site. TM 4 15-Jan-07
8 3 SVG RH Fit 'no horse riding' signs at tracks leading off byway. HT 0.25  
9 3 SVG RH Harebell Corner. Clear next section of shading trees on southwest side of area, and going through into Long Glade. Create new, or extend existing, log pile. Burn brash. CS, TT 5 29-Jan-07
10 3 SVG RH Harebell Corner. Cut grass areas during October or November. Clear arisings as green hay to local area cleared last year. M, HT 1 29-Jan-07
11 3 SVG RH Upper Quarry. Cut back birch re-growth. Establish 4 year cycle to cut 50% biennially. Clear brash to local burn site. M, TT 1 26-Feb-07
12 3 SVG RH Lower Wood Glade. Cut and clear. Clear arisings to local compost site. BC, HT, TT 2 12-Feb-07
13 3 SVG RH Spur 1. Cut back bramble re-growth in Spur 1 scollops.  Clear to Compost Hollow. BC,TT 1 12-Feb-07
14 3 SVG RH Upper Quarry. Establish 4 year cycle to cut 50% biennially. Clear brash to local burn site. HT, TT 1 12-Feb-07
15 0 SVG RH Lower Quarry. Establish 4 year cycle to cut and clear dense grass areas and bramble spread. Clear arisings to Compost Hollow. M, TT 1  
16 3 SVG RH Walden Hill. Cut and clear to compost hollow. TM,TB,TT 5 16-Oct-06
17 3 SVG RH Spur 1. Cut back bramble spreading onto spur 1 next to Nassington Bottoms Close. Clear to Compost Hollow. HT 1 19-Feb-07
18 3 SVG RH Walden Lane - near south gate. Cut back scrub spreading across stock fencing and Walden Lane from by-way side. Clear brash back into wooded area between by-way and stock fence. HT 1 26-Feb-07
19 4 SVG RH Build section of fencing with stile (or dead hedging with chicane) at footpath leading off Byway (between Bracken Wood and Nightingale Scrub). Advise WLT of materials required. HT, TT 2  
20 4 SVG RH Calcining Banks. Pollard willow and clear spreading elder/hawthorn/blackthorn ajacent to footpath between Calcining Banks and Nassington Bottoms Close. Create local log pile, and clear brash to local burn site. CS, TT, HT 1 8-Jan-07
21 4 SVG RH Clear posts near FP between Nassington Bottoms Close and Calcining Banks. TT 0.25 18-Dec-06
22 4 SVG RH Map new fence line on east side Nassinton Bottoms Mire HT 0.5  
23 4 SVG RH Pheasant Pen. Coppice an area adjacent to, and to the east of the previous cleared area. Build log pile. Burn brash locally. CS, TT 5 5-Feb-07
24 0 SVG RH Burn brash at Upper Quarry burn site. HT 0.5  
25 5 SVG RH Burn brash etc at Harebell Corner burn site. HT 0.5 29-Jan-07
26 5 SVG RH Burn brash/arisings at Calcining Banks local burn site. HT 0.5 15-Jan-07
27 S SVG RH Pheasant pen. Cut back bracken to keep grassy areas clear. Clear to local burn site. BC, HT 0.5  
28   WLT RH Reorganise large bales in Compost Hollow OR clear trees to provide access behind bales.      
29 0 SVG SF Mucky Ride. Re-fix loose interpretation board at lower end of ride. HT 0.25 see item 38
30 2 SVG SF Cut bramble re-growth on Mucky Ride. Clear to brash pile in wood. M, HT 1 11-Dec-06
31 0 WLT SF Ref. fallen branches from oak tree near permissive path in King's Oaks (grid ref TL621827). Ensure safe, clear branches that restrict path. CS, TT 0.5  
32 3 SVG SF Clear ash saplings that are laning over the bridleway (primarily to the east of Chestnut Meet). Clear to brash pile in wood.     22-Jan-07
33 3 SVG SF Clear tree fallen across dry stone wall (grid ref TL666861). Clear to pile in forest. CS, TT 0.25 22-Jan-07
34 3 SVG SF Clear tree guards around tree bases in Cow Wood (3 trees affected). HT 0.25  
35 3 SVG SF Install posts, and fit 'no horse riding' signs at tracks leading off bridleways. HT 0.5  
36 3 SVG SF Mow ride edge through Sulehay. Cut back any excessive overhang. Clear arisings and brash to suitable piles in forest. M, HT 1 11-Dec-06
37 3 SVG SF Mucky Ride. Extend ride side clearance by removing trees/shrubs up to and on to the banks, but leaving established oak trees. For hazel, start a 4 year copicing routine, with 2 year gap between alternate plants along the ride. Clear to brash pile in wood.     22-Jan-07
38 3 SVG SF Mucky Ride. Re-fix loose interpretation board at lower end of ride. HT 0.25  
39 3 SVG SF SF Scollop 01 annual mowing (grassland). Clear arisings to suitable pile inside wood. M or BC 0.25 11-Dec-06
40 3 SVG SF SF Scollop 02 annual mowing (grassland). Clear arisings to suitable pile inside wood. M or BC 0.25 11-Dec-06
41 3 SVG SF SF Scollop 05 annual mowing (grassland). Clear arisings to suitable pile inside wood. M or BC 0.25 11-Dec-06
42 3 SVG SF SF Scollop 12 annual mowing (grassland). Clear arisings to suitable pile inside wood. M or BC 0.25 11-Dec-06
43 3 SVG SF SF Scollop 18 annual mowing (grassland). Clear arisings to suitable pile inside wood. M or BC 0.25 11-Dec-06
44 4 SVG SF Clear old pheasant pen posts, netting and palettes to RH storage area. TT 1  
45 4 SVG SF Clear remaining old post and rail fencing materials to RH storage area. TT 0.5 In progress
46 4 SVG SF Cut and clear sycamore regrowth in area previously cleared in Yarwell Quarter. Continue to clear sycamore saplings throughout Yarwell Quarter. Clear to local bash pile. HT 2  
47 4 WLT SF Identify suitable area(s) of woodland for coppicing to create varied habitat (woodland clearings). WLT to discuss with 'Natural England' ref SSSI. CS, TT 5  
48 5   SF Clear old bottles and glass debris from west end Cow Wood. HT, TT    
49 5   SF Continue repair to drystone wall on SF east side HT    
50 0 SVG SQ Cut area of Primrose Hill currently overgrown with bramble and clematis. Clear arisings to local burn site. M or HT, TT 2 see item 56
51 2 PCV SQ Kissing gate. Clear bramble etc at access to Bridleway from opposite Sulehay Lodge. Clear brash to local burn site. HT, TT 0.25 1-Oct-06
52 2 SVG SQ Kissing gate. Clear bramble etc at access to SQ from Sulehay road. Clear brash to local burn site. HT, TT 0.25 5-Mar-07
53 2 SVG SQ Primrose Hill. Keep West Path clear. Clear brash to local burn site. M or HT, TT 0.5 5-Mar-07
54 3 PCV SQ Bridleway. Cut back hedging on north side. Clear brash back into hedge to act as dead hedging. HT 1 1-Oct-06
55 3 SVG SQ Primrose Hill. Clear an area of bramble and old man's beard between West Path, and Sulehay Road, and to the south of Primrose Hill. Clear arisings to local burn site. HT 1 5-Mar-07
56 3 PCV/SVG SQ Cut back birch re-growth in Bareground Bottom and adjacent to Birch Hollow and East Path. Establish 4 year cycle to cut 50% biennially. Clear brash to local burn site. HT, TT 1 31-Dec-06
57 3 SVG SQ Bridleway. Cut back bramble re-growth inside stock fencing. BC, HT 1  
58 3 SVG SQ Bridleway. Mow ride edge through Stonepit Quarry. M. HT 0.5 11-Dec-06
59 3 SVG SQ Collect old logs and stumps and take to burn site in quarry area. TT 0.5  
60 4 SVG SQ Cut and clear sycamore re-growth. Treat stumps to inhibit future re-growth. Clear to local burn site. HT, TT 0.25  
61 4 SVG SQ Kissing gate. Repair kissing gate leading into SQ from Quarry Ride (east end).  Advise WLT of materials required. HT, TT 2  
62 4 SVG SQ Mow and rake Fairy Flax walk. Clear to burn site. M, HT 0.5  
63 5 PCV/SVG SQ Burn brash and arisings collected from clearing activities. HT 0.5 In progress
64 3 SVG SQ Clear ivy covered blackthorn (?) fallen onto edge of Stonepit Quarry Ride. HT 0.25 5-Mar-07
Total days estimated for all tasks: 61.75
Total days available @ 1 day per week through October 2006 to March 2007 inclusive: 24